4.5.23: Scenario 24 – Scope Reconciliation and Stakeholder Conflict
- Page ID
- 54830
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\( \newcommand{\dsum}{\displaystyle\sum\limits} \)
\( \newcommand{\dint}{\displaystyle\int\limits} \)
\( \newcommand{\dlim}{\displaystyle\lim\limits} \)
\( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)
( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\id}{\mathrm{id}}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\kernel}{\mathrm{null}\,}\)
\( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\)
\( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\)
\( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)
\( \newcommand{\vectorA}[1]{\vec{#1}} % arrow\)
\( \newcommand{\vectorAt}[1]{\vec{\text{#1}}} % arrow\)
\( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vectorC}[1]{\textbf{#1}} \)
\( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)
\( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)
\( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\(\newcommand{\longvect}{\overrightarrow}\)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\(\newcommand{\ket}[1]{\left| #1 \right>}\)
\(\newcommand{\bra}[1]{\left< #1 \right|}\)
\(\newcommand{\braket}[2]{\left< #1 \vphantom{#2} \right| \left. #2 \vphantom{#1} \right>}\)
\(\newcommand{\braopket}[3]{\left< #1 \vphantom{#2}\vphantom{#3} \right| #2 \vphantom{#1}\vphantom{#3} \left| #3 \vphantom{#1}\vphantom{#2} \right>}\)
\(\newcommand{\qmvec}[1]{\mathbf{\vec{#1}}}\)
\(\newcommand{\op}[1]{\hat{\mathbf{#1}}}\)
\(\newcommand{\expect}[1]{\langle #1 \rangle}\)
\(\newcommand{\dfn}[1]{\emph{\textbf{#1}}}\)
Scenario Context
Following identification of scope drift in Scenario 23, a formal review of project scope has been initiated.
The review revealed:
- Several features implemented that were not formally approved
- Some features partially implemented based on informal discussions
- Differences between documented scope and delivered functionality
As part of restoring control, a scope reconciliation effort has been conducted.
However, this process has surfaced conflicting stakeholder expectations.
Email from Julie Rama
Subject: Scope Reconciliation – Alignment Required
Hi,
Following your direction, we conducted a reconciliation of current delivered functionality against the original project scope and approved backlog.
Reconciliation Findings
We identified three categories:
Category A – In Scope (Aligned)
- Core project features
- Approved backlog items
Category B – Informally Added Enhancements
- Reporting flexibility features
- Minor UI customization
- Additional filtering capabilities
Category C – Partially Implemented Requests
- Features discussed but not formally defined
- Some incomplete functionality
Stakeholder Feedback
We have received feedback from stakeholders indicating that:
- Enhancements currently in the system are now considered expected functionality
- Removal or deferral of these features would be viewed negatively
- Some partially implemented features are now assumed to be part of the product
Impact
If we attempt to:
- Roll back enhancements → Stakeholder dissatisfaction likely
- Formalize all enhancements → Budget and schedule impact
- Leave as-is → Scope and baseline remain unclear
Vendor Position
We can proceed with any direction, but we need clarity on:
- What constitutes final scope
- How to handle partially implemented features
- Whether additional effort will be approved
Request
Please advise how you would like to resolve:
- Scope alignment
- Stakeholder expectations
- Baseline definition moving forward
Best,
Julie
Attachment A – Scope Categories
| Category | Description | Status |
|---|---|---|
| A | Approved Scope | Complete |
| B | Informal Enhancements | Delivered |
| C | Partial Features | Incomplete |
Attachment B – Stakeholder Input
- “These reporting features are already in the system — they should remain.”
- “We expected these capabilities as part of the release.”
- “Removing features now would reduce confidence.”
Student Assignment
You are the Project Manager at C-Bay.
You are now facing:
- Formal scope reconciliation
- Stakeholders resisting rollback
- Partially implemented features creating ambiguity
- Budget and schedule implications
You must determine:
- What the final scope should be
- How to resolve stakeholder conflict
- Whether to formalize, defer, or remove features
- How to restore control without damaging confidence
Prepare a formal written response to Julie Rama.
Required Submission Structure
Your memorandum must include:
Executive Position
- Is scope alignment achievable?
- How should conflict be resolved?
- What is your position on current scope state?
Scope Resolution Strategy
Choose and justify:
- Accept all enhancements and reset baseline
- Retain only selected enhancements
- Remove or defer certain features
- Formalize partial features through change control
Stakeholder Management Strategy
- How will you handle stakeholder resistance?
- How will you communicate scope decisions?
- How will you maintain confidence?
Budget & Schedule Impact
- What is the cost of formalizing enhancements?
- What is the impact of retaining all features?
- What trade-offs are required?
Risk Assessment
Identify and evaluate:
- Scope ambiguity risk
- Stakeholder dissatisfaction risk
- Budget escalation risk
- Delivery instability risk
Assign likelihood and impact.
Control Restoration Plan
- How will you re-establish scope control?
- What processes will be enforced going forward?
- How will you prevent future drift?
Directive to ZynoxDev
Provide a clear directive, such as:
- Formalize selected enhancements through change control
- Complete partially implemented features under approved scope
- Defer non-critical enhancements
- Reset baseline and update documentation
- Freeze further informal changes
Learning Focus
Scenario 24 introduces:
- Conflict between delivery reality and expectations
- Stakeholder resistance to scope correction
- Managing partially completed work
- Formalizing informal decisions
- Re-establishing control under pressure
Students must demonstrate:
- Conflict resolution
- Structured negotiation
- Scope clarity
- Leadership under tension
Key Insight
Once features exist, they become expectations.
Even if they were never approved.
This scenario reinforces:
Controlling scope early is easier than correcting it later.