4.5.24: Scenario 25 – Baseline Reset and Contract Realignment
- Page ID
- 54831
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\( \newcommand{\dsum}{\displaystyle\sum\limits} \)
\( \newcommand{\dint}{\displaystyle\int\limits} \)
\( \newcommand{\dlim}{\displaystyle\lim\limits} \)
\( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)
( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\id}{\mathrm{id}}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\kernel}{\mathrm{null}\,}\)
\( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\)
\( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\)
\( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)
\( \newcommand{\vectorA}[1]{\vec{#1}} % arrow\)
\( \newcommand{\vectorAt}[1]{\vec{\text{#1}}} % arrow\)
\( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vectorC}[1]{\textbf{#1}} \)
\( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)
\( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)
\( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\(\newcommand{\longvect}{\overrightarrow}\)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\(\newcommand{\ket}[1]{\left| #1 \right>}\)
\(\newcommand{\bra}[1]{\left< #1 \right|}\)
\(\newcommand{\braket}[2]{\left< #1 \vphantom{#2} \right| \left. #2 \vphantom{#1} \right>}\)
\(\newcommand{\braopket}[3]{\left< #1 \vphantom{#2}\vphantom{#3} \right| #2 \vphantom{#1}\vphantom{#3} \left| #3 \vphantom{#1}\vphantom{#2} \right>}\)
\(\newcommand{\qmvec}[1]{\mathbf{\vec{#1}}}\)
\(\newcommand{\op}[1]{\hat{\mathbf{#1}}}\)
\(\newcommand{\expect}[1]{\langle #1 \rangle}\)
\(\newcommand{\dfn}[1]{\emph{\textbf{#1}}}\)
Scenario Context
Following scope reconciliation and stakeholder conflict in Scenario 24, it is now clear that:
- The original scope baseline is no longer accurate
- Informal enhancements have become embedded in the system
- Stakeholder expectations have evolved
- Budget and schedule assumptions have shifted
C-Bay has initiated a formal realignment effort to:
- Reset scope baseline
- Clarify deliverables
- Reconcile cost and schedule
- Establish clear control moving forward
ZynoxDev has responded with a formal proposal.
Email from Julie Rama
Subject: Project Realignment Proposal – Scope, Schedule, and Cost
Hi,
Following the recent scope reconciliation discussions, we have prepared a proposal to align the project moving forward.
Proposed Scope Baseline
We recommend redefining the project scope as follows:
- Core Features (Original Scope) → Completed
- Enhancements (Previously Informal) → Included as formal scope
- Partial Features → Completed or removed based on prioritization
This reflects the system as it currently exists and stakeholder expectations.
Schedule Realignment
To accommodate the expanded scope and stabilization efforts:
- Revised delivery timeline: +2 weeks beyond original plan
- Adjusted milestone checkpoints for future iterations
Budget Adjustment
Based on current effort and scope expansion:
- Proposed budget increase: +12–14%
- Reflects:
- Additional development effort
- Increased QA cycles
- Refactoring and stabilization work
Control Measures
To prevent further drift, we propose:
- Strict change control for all future enhancements
- Formal backlog prioritization reviews
- Defined iteration scope boundaries
Request
Please review and confirm:
- Acceptance of revised scope baseline
- Approval of schedule adjustment
- Approval of budget realignment
We believe this will establish a stable foundation moving forward.
Best,
Julie
Attachment A – Realignment Summary
| Area | Original | Revised |
|---|---|---|
| Scope | URD-defined | Expanded (includes enhancements) |
| Schedule | Original timeline | +2 weeks |
| Budget | Baseline | +12–14% |
Attachment B – Control Measures
- Formal change request process required for all new features
- Backlog review at start of each iteration
- No in-iteration scope adjustments allowed
Student Assignment
You are the Project Manager at C-Bay.
You must now decide whether to:
- Accept the proposed realignment
- Modify the proposal
- Reject elements of the proposal
This decision will define:
- The new baseline for the project
- The credibility of project control moving forward
- The relationship with ZynoxDev
You must evaluate:
- Whether the proposed scope is acceptable
- Whether budget increase is justified
- Whether schedule adjustment is reasonable
- Whether control measures are sufficient
Prepare a formal written response to Julie Rama.
Required Submission Structure
Your memorandum must include:
Executive Position
- Do you accept the realignment proposal?
- What elements do you approve or reject?
- Is the project now under control?
Scope Decision
- Should all enhancements be formalized into scope?
- Should any features be removed or deferred?
- Is the revised scope appropriate?
Budget & Schedule Decision
- Is +12–14% budget increase justified?
- Is a +2 week delay acceptable?
- Should adjustments be negotiated?
Contract & Control Alignment
- Are proposed control measures sufficient?
- Should additional controls be introduced?
- How will future drift be prevented?
Risk Assessment
Identify and evaluate:
- Budget overrun risk
- Schedule extension risk
- Scope misalignment risk
- Governance failure risk
Assign likelihood and impact.
Strategic Positioning
- How will you communicate this realignment internally?
- How will you justify the changes to leadership?
- How will you restore confidence in project control?
Directive to ZynoxDev
Provide a clear directive, such as:
- Approve full realignment
- Approve with modifications
- Reject certain scope elements
- Require revised proposal
- Implement additional governance controls
Learning Focus
Scenario 25 introduces:
- Formal baseline reset
- Contract realignment
- Converting informal history into structured agreement
- Negotiation of cost, scope, and schedule simultaneously
- Establishing control after drift
Students must demonstrate:
- Strategic negotiation
- Decision ownership
- Balance between acceptance and control
- Long-term thinking
Key Insight
A project can only be controlled once reality is acknowledged.
This scenario reinforces:
You cannot manage what is no longer aligned with the plan.
You must:
- Update the plan
- Or restore the plan
This marks a major turning point in the practicum.