4.5.25: Scenario 24 – Scope Reconciliation and Stakeholder Conflict
- Page ID
- 54830
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\( \newcommand{\dsum}{\displaystyle\sum\limits} \)
\( \newcommand{\dint}{\displaystyle\int\limits} \)
\( \newcommand{\dlim}{\displaystyle\lim\limits} \)
\( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)
( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\id}{\mathrm{id}}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\kernel}{\mathrm{null}\,}\)
\( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\)
\( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\)
\( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)
\( \newcommand{\vectorA}[1]{\vec{#1}} % arrow\)
\( \newcommand{\vectorAt}[1]{\vec{\text{#1}}} % arrow\)
\( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vectorC}[1]{\textbf{#1}} \)
\( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)
\( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)
\( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\(\newcommand{\longvect}{\overrightarrow}\)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\(\newcommand{\avec}{\mathbf a}\) \(\newcommand{\bvec}{\mathbf b}\) \(\newcommand{\cvec}{\mathbf c}\) \(\newcommand{\dvec}{\mathbf d}\) \(\newcommand{\dtil}{\widetilde{\mathbf d}}\) \(\newcommand{\evec}{\mathbf e}\) \(\newcommand{\fvec}{\mathbf f}\) \(\newcommand{\nvec}{\mathbf n}\) \(\newcommand{\pvec}{\mathbf p}\) \(\newcommand{\qvec}{\mathbf q}\) \(\newcommand{\svec}{\mathbf s}\) \(\newcommand{\tvec}{\mathbf t}\) \(\newcommand{\uvec}{\mathbf u}\) \(\newcommand{\vvec}{\mathbf v}\) \(\newcommand{\wvec}{\mathbf w}\) \(\newcommand{\xvec}{\mathbf x}\) \(\newcommand{\yvec}{\mathbf y}\) \(\newcommand{\zvec}{\mathbf z}\) \(\newcommand{\rvec}{\mathbf r}\) \(\newcommand{\mvec}{\mathbf m}\) \(\newcommand{\zerovec}{\mathbf 0}\) \(\newcommand{\onevec}{\mathbf 1}\) \(\newcommand{\real}{\mathbb R}\) \(\newcommand{\twovec}[2]{\left[\begin{array}{r}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\ctwovec}[2]{\left[\begin{array}{c}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\threevec}[3]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\cthreevec}[3]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\fourvec}[4]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\cfourvec}[4]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\fivevec}[5]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\cfivevec}[5]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\mattwo}[4]{\left[\begin{array}{rr}#1 \amp #2 \\ #3 \amp #4 \\ \end{array}\right]}\) \(\newcommand{\laspan}[1]{\text{Span}\{#1\}}\) \(\newcommand{\bcal}{\cal B}\) \(\newcommand{\ccal}{\cal C}\) \(\newcommand{\scal}{\cal S}\) \(\newcommand{\wcal}{\cal W}\) \(\newcommand{\ecal}{\cal E}\) \(\newcommand{\coords}[2]{\left\{#1\right\}_{#2}}\) \(\newcommand{\gray}[1]{\color{gray}{#1}}\) \(\newcommand{\lgray}[1]{\color{lightgray}{#1}}\) \(\newcommand{\rank}{\operatorname{rank}}\) \(\newcommand{\row}{\text{Row}}\) \(\newcommand{\col}{\text{Col}}\) \(\renewcommand{\row}{\text{Row}}\) \(\newcommand{\nul}{\text{Nul}}\) \(\newcommand{\var}{\text{Var}}\) \(\newcommand{\corr}{\text{corr}}\) \(\newcommand{\len}[1]{\left|#1\right|}\) \(\newcommand{\bbar}{\overline{\bvec}}\) \(\newcommand{\bhat}{\widehat{\bvec}}\) \(\newcommand{\bperp}{\bvec^\perp}\) \(\newcommand{\xhat}{\widehat{\xvec}}\) \(\newcommand{\vhat}{\widehat{\vvec}}\) \(\newcommand{\uhat}{\widehat{\uvec}}\) \(\newcommand{\what}{\widehat{\wvec}}\) \(\newcommand{\Sighat}{\widehat{\Sigma}}\) \(\newcommand{\lt}{<}\) \(\newcommand{\gt}{>}\) \(\newcommand{\amp}{&}\) \(\definecolor{fillinmathshade}{gray}{0.9}\)Scenario 24 – Scope Reconciliation and Stakeholder Conflict
Scenario Context
Following identification of scope drift in Scenario 23, a formal review of project scope has been initiated.
The review revealed:
-
Several features implemented that were not formally approved
-
Some features partially implemented based on informal discussions
-
Differences between documented scope and delivered functionality
As part of restoring control, a scope reconciliation effort has been conducted.
However, this process has surfaced conflicting stakeholder expectations.
Email from Julie Rama
Subject: Scope Reconciliation – Alignment Required
Hi,
Following your direction, we conducted a reconciliation of current delivered functionality against the original project scope and approved backlog.
1. Reconciliation Findings
We identified three categories:
Category A – In Scope (Aligned)
-
Core project features
-
Approved backlog items
Category B – Informally Added Enhancements
-
Reporting flexibility features
-
Minor UI customization
-
Additional filtering capabilities
Category C – Partially Implemented Requests
-
Features discussed but not formally defined
-
Some incomplete functionality
2. Stakeholder Feedback
We have received feedback from stakeholders indicating that:
-
Enhancements currently in the system are now considered expected functionality
-
Removal or deferral of these features would be viewed negatively
-
Some partially implemented features are now assumed to be part of the product
3. Impact
If we attempt to:
-
Roll back enhancements → Stakeholder dissatisfaction likely
-
Formalize all enhancements → Budget and schedule impact
-
Leave as-is → Scope and baseline remain unclear
4. Vendor Position
We can proceed with any direction, but we need clarity on:
-
What constitutes final scope
-
How to handle partially implemented features
-
Whether additional effort will be approved
5. Request
Please advise how you would like to resolve:
-
Scope alignment
-
Stakeholder expectations
-
Baseline definition moving forward
Best,
Julie
Attachment A – Scope Categories
| Category | Description | Status |
|---|---|---|
| A | Approved Scope | Complete |
| B | Informal Enhancements | Delivered |
| C | Partial Features | Incomplete |
Attachment B – Stakeholder Input
-
“These reporting features are already in the system — they should remain.”
-
“We expected these capabilities as part of the release.”
-
“Removing features now would reduce confidence.”
Student Assignment
You are the Project Manager at C-Bay.
You are now facing:
-
Formal scope reconciliation
-
Stakeholders resisting rollback
-
Partially implemented features creating ambiguity
-
Budget and schedule implications
You must determine:
-
What the final scope should be
-
How to resolve stakeholder conflict
-
Whether to formalize, defer, or remove features
-
How to restore control without damaging confidence
Prepare a formal written response to Julie Rama.
Required Submission Structure
Your memorandum must include:
1️⃣ Executive Position
-
Is scope alignment achievable?
-
How should conflict be resolved?
-
What is your position on current scope state?
2️⃣ Scope Resolution Strategy
Choose and justify:
-
Accept all enhancements and reset baseline
-
Retain only selected enhancements
-
Remove or defer certain features
-
Formalize partial features through change control
3️⃣ Stakeholder Management Strategy
-
How will you handle stakeholder resistance?
-
How will you communicate scope decisions?
-
How will you maintain confidence?
4️⃣ Budget & Schedule Impact
-
What is the cost of formalizing enhancements?
-
What is the impact of retaining all features?
-
What trade-offs are required?
5️⃣ Risk Assessment
Identify and evaluate:
-
Scope ambiguity risk
-
Stakeholder dissatisfaction risk
-
Budget escalation risk
-
Delivery instability risk
Assign likelihood and impact.
6️⃣ Control Restoration Plan
-
How will you re-establish scope control?
-
What processes will be enforced going forward?
-
How will you prevent future drift?
7️⃣ Directive to ZynoxDev
Provide a clear directive, such as:
-
Formalize selected enhancements through change control
-
Complete partially implemented features under approved scope
-
Defer non-critical enhancements
-
Reset baseline and update documentation
-
Freeze further informal changes
Learning Focus
Scenario 24 introduces:
-
Conflict between delivery reality and expectations
-
Stakeholder resistance to scope correction
-
Managing partially completed work
-
Formalizing informal decisions
-
Re-establishing control under pressure
Students must demonstrate:
-
Conflict resolution
-
Structured negotiation
-
Scope clarity
-
Leadership under tension
Key Insight
Once features exist, they become expectations.
Even if they were never approved.
This scenario reinforces:
Controlling scope early is easier than correcting it later.

