Skip to main content
Workforce LibreTexts

4.5.26: Scenario 25 – Baseline Reset and Contract Realignment

  • Page ID
    54831
  • \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \( \newcommand{\dsum}{\displaystyle\sum\limits} \)

    \( \newcommand{\dint}{\displaystyle\int\limits} \)

    \( \newcommand{\dlim}{\displaystyle\lim\limits} \)

    \( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)

    ( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\id}{\mathrm{id}}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\kernel}{\mathrm{null}\,}\)

    \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\)

    \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\)

    \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)

    \( \newcommand{\vectorA}[1]{\vec{#1}}      % arrow\)

    \( \newcommand{\vectorAt}[1]{\vec{\text{#1}}}      % arrow\)

    \( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vectorC}[1]{\textbf{#1}} \)

    \( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)

    \( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)

    \( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)

    \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \(\newcommand{\longvect}{\overrightarrow}\)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \(\newcommand{\avec}{\mathbf a}\) \(\newcommand{\bvec}{\mathbf b}\) \(\newcommand{\cvec}{\mathbf c}\) \(\newcommand{\dvec}{\mathbf d}\) \(\newcommand{\dtil}{\widetilde{\mathbf d}}\) \(\newcommand{\evec}{\mathbf e}\) \(\newcommand{\fvec}{\mathbf f}\) \(\newcommand{\nvec}{\mathbf n}\) \(\newcommand{\pvec}{\mathbf p}\) \(\newcommand{\qvec}{\mathbf q}\) \(\newcommand{\svec}{\mathbf s}\) \(\newcommand{\tvec}{\mathbf t}\) \(\newcommand{\uvec}{\mathbf u}\) \(\newcommand{\vvec}{\mathbf v}\) \(\newcommand{\wvec}{\mathbf w}\) \(\newcommand{\xvec}{\mathbf x}\) \(\newcommand{\yvec}{\mathbf y}\) \(\newcommand{\zvec}{\mathbf z}\) \(\newcommand{\rvec}{\mathbf r}\) \(\newcommand{\mvec}{\mathbf m}\) \(\newcommand{\zerovec}{\mathbf 0}\) \(\newcommand{\onevec}{\mathbf 1}\) \(\newcommand{\real}{\mathbb R}\) \(\newcommand{\twovec}[2]{\left[\begin{array}{r}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\ctwovec}[2]{\left[\begin{array}{c}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\threevec}[3]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\cthreevec}[3]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\fourvec}[4]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\cfourvec}[4]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\fivevec}[5]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\cfivevec}[5]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\mattwo}[4]{\left[\begin{array}{rr}#1 \amp #2 \\ #3 \amp #4 \\ \end{array}\right]}\) \(\newcommand{\laspan}[1]{\text{Span}\{#1\}}\) \(\newcommand{\bcal}{\cal B}\) \(\newcommand{\ccal}{\cal C}\) \(\newcommand{\scal}{\cal S}\) \(\newcommand{\wcal}{\cal W}\) \(\newcommand{\ecal}{\cal E}\) \(\newcommand{\coords}[2]{\left\{#1\right\}_{#2}}\) \(\newcommand{\gray}[1]{\color{gray}{#1}}\) \(\newcommand{\lgray}[1]{\color{lightgray}{#1}}\) \(\newcommand{\rank}{\operatorname{rank}}\) \(\newcommand{\row}{\text{Row}}\) \(\newcommand{\col}{\text{Col}}\) \(\renewcommand{\row}{\text{Row}}\) \(\newcommand{\nul}{\text{Nul}}\) \(\newcommand{\var}{\text{Var}}\) \(\newcommand{\corr}{\text{corr}}\) \(\newcommand{\len}[1]{\left|#1\right|}\) \(\newcommand{\bbar}{\overline{\bvec}}\) \(\newcommand{\bhat}{\widehat{\bvec}}\) \(\newcommand{\bperp}{\bvec^\perp}\) \(\newcommand{\xhat}{\widehat{\xvec}}\) \(\newcommand{\vhat}{\widehat{\vvec}}\) \(\newcommand{\uhat}{\widehat{\uvec}}\) \(\newcommand{\what}{\widehat{\wvec}}\) \(\newcommand{\Sighat}{\widehat{\Sigma}}\) \(\newcommand{\lt}{<}\) \(\newcommand{\gt}{>}\) \(\newcommand{\amp}{&}\) \(\definecolor{fillinmathshade}{gray}{0.9}\)

    Scenario 25 – Baseline Reset and Contract Realignment


    Scenario Context

    Following scope reconciliation and stakeholder conflict in Scenario 24, it is now clear that:

    • The original scope baseline is no longer accurate

    • Informal enhancements have become embedded in the system

    • Stakeholder expectations have evolved

    • Budget and schedule assumptions have shifted

    C-Bay has initiated a formal realignment effort to:

    • Reset scope baseline

    • Clarify deliverables

    • Reconcile cost and schedule

    • Establish clear control moving forward

    ZynoxDev has responded with a formal proposal.


    Email from Julie Rama

    Subject: Project Realignment Proposal – Scope, Schedule, and Cost

    Hi,

    Following the recent scope reconciliation discussions, we have prepared a proposal to align the project moving forward.


    1. Proposed Scope Baseline

    We recommend redefining the project scope as follows:

    • Core Features (Original Scope) → Completed

    • Enhancements (Previously Informal) → Included as formal scope

    • Partial Features → Completed or removed based on prioritization

    This reflects the system as it currently exists and stakeholder expectations.


    2. Schedule Realignment

    To accommodate the expanded scope and stabilization efforts:

    • Revised delivery timeline: +2 weeks beyond original plan

    • Adjusted milestone checkpoints for future iterations


    3. Budget Adjustment

    Based on current effort and scope expansion:

    • Proposed budget increase: +12–14%

    • Reflects:

      • Additional development effort

      • Increased QA cycles

      • Refactoring and stabilization work


    4. Control Measures

    To prevent further drift, we propose:

    • Strict change control for all future enhancements

    • Formal backlog prioritization reviews

    • Defined iteration scope boundaries


    5. Request

    Please review and confirm:

    • Acceptance of revised scope baseline

    • Approval of schedule adjustment

    • Approval of budget realignment

    We believe this will establish a stable foundation moving forward.

    Best,
    Julie


    Attachment A – Realignment Summary

    Area Original Revised
    Scope URD-defined Expanded (includes enhancements)
    Schedule Original timeline +2 weeks
    Budget Baseline +12–14%

    Attachment B – Control Measures

    • Formal change request process required for all new features

    • Backlog review at start of each iteration

    • No in-iteration scope adjustments allowed


    Student Assignment

    You are the Project Manager at C-Bay.

    You must now decide whether to:

    • Accept the proposed realignment

    • Modify the proposal

    • Reject elements of the proposal

    This decision will define:

    • The new baseline for the project

    • The credibility of project control moving forward

    • The relationship with ZynoxDev

    You must evaluate:

    • Whether the proposed scope is acceptable

    • Whether budget increase is justified

    • Whether schedule adjustment is reasonable

    • Whether control measures are sufficient

    Prepare a formal written response to Julie Rama.


    Required Submission Structure

    Your memorandum must include:


    1️⃣ Executive Position

    • Do you accept the realignment proposal?

    • What elements do you approve or reject?

    • Is the project now under control?


    2️⃣ Scope Decision

    • Should all enhancements be formalized into scope?

    • Should any features be removed or deferred?

    • Is the revised scope appropriate?


    3️⃣ Budget & Schedule Decision

    • Is +12–14% budget increase justified?

    • Is a +2 week delay acceptable?

    • Should adjustments be negotiated?


    4️⃣ Contract & Control Alignment

    • Are proposed control measures sufficient?

    • Should additional controls be introduced?

    • How will future drift be prevented?


    5️⃣ Risk Assessment

    Identify and evaluate:

    • Budget overrun risk

    • Schedule extension risk

    • Scope misalignment risk

    • Governance failure risk

    Assign likelihood and impact.


    6️⃣ Strategic Positioning

    • How will you communicate this realignment internally?

    • How will you justify the changes to leadership?

    • How will you restore confidence in project control?


    7️⃣ Directive to ZynoxDev

    Provide a clear directive, such as:

    • Approve full realignment

    • Approve with modifications

    • Reject certain scope elements

    • Require revised proposal

    • Implement additional governance controls


    Learning Focus

    Scenario 25 introduces:

    • Formal baseline reset

    • Contract realignment

    • Converting informal history into structured agreement

    • Negotiation of cost, scope, and schedule simultaneously

    • Establishing control after drift

    Students must demonstrate:

    • Strategic negotiation

    • Decision ownership

    • Balance between acceptance and control

    • Long-term thinking


    Key Insight

    A project can only be controlled once reality is acknowledged.


    This scenario reinforces:

    You cannot manage what is no longer aligned with the plan.

    You must:

    • Update the plan

    • Or restore the plan


    This marks a major turning point in the practicum.


    4.5.26: Scenario 25 – Baseline Reset and Contract Realignment is shared under a CC BY 4.0 license and was authored, remixed, and/or curated by LibreTexts.