4.5.26: Scenario 25 – Baseline Reset and Contract Realignment
- Page ID
- 54831
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\( \newcommand{\dsum}{\displaystyle\sum\limits} \)
\( \newcommand{\dint}{\displaystyle\int\limits} \)
\( \newcommand{\dlim}{\displaystyle\lim\limits} \)
\( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)
( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\id}{\mathrm{id}}\)
\( \newcommand{\Span}{\mathrm{span}}\)
\( \newcommand{\kernel}{\mathrm{null}\,}\)
\( \newcommand{\range}{\mathrm{range}\,}\)
\( \newcommand{\RealPart}{\mathrm{Re}}\)
\( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)
\( \newcommand{\Argument}{\mathrm{Arg}}\)
\( \newcommand{\norm}[1]{\| #1 \|}\)
\( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)
\( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)
\( \newcommand{\vectorA}[1]{\vec{#1}} % arrow\)
\( \newcommand{\vectorAt}[1]{\vec{\text{#1}}} % arrow\)
\( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\( \newcommand{\vectorC}[1]{\textbf{#1}} \)
\( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)
\( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)
\( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)
\( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)
\(\newcommand{\longvect}{\overrightarrow}\)
\( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)
\(\newcommand{\avec}{\mathbf a}\) \(\newcommand{\bvec}{\mathbf b}\) \(\newcommand{\cvec}{\mathbf c}\) \(\newcommand{\dvec}{\mathbf d}\) \(\newcommand{\dtil}{\widetilde{\mathbf d}}\) \(\newcommand{\evec}{\mathbf e}\) \(\newcommand{\fvec}{\mathbf f}\) \(\newcommand{\nvec}{\mathbf n}\) \(\newcommand{\pvec}{\mathbf p}\) \(\newcommand{\qvec}{\mathbf q}\) \(\newcommand{\svec}{\mathbf s}\) \(\newcommand{\tvec}{\mathbf t}\) \(\newcommand{\uvec}{\mathbf u}\) \(\newcommand{\vvec}{\mathbf v}\) \(\newcommand{\wvec}{\mathbf w}\) \(\newcommand{\xvec}{\mathbf x}\) \(\newcommand{\yvec}{\mathbf y}\) \(\newcommand{\zvec}{\mathbf z}\) \(\newcommand{\rvec}{\mathbf r}\) \(\newcommand{\mvec}{\mathbf m}\) \(\newcommand{\zerovec}{\mathbf 0}\) \(\newcommand{\onevec}{\mathbf 1}\) \(\newcommand{\real}{\mathbb R}\) \(\newcommand{\twovec}[2]{\left[\begin{array}{r}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\ctwovec}[2]{\left[\begin{array}{c}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\threevec}[3]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\cthreevec}[3]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\fourvec}[4]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\cfourvec}[4]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\fivevec}[5]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\cfivevec}[5]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\mattwo}[4]{\left[\begin{array}{rr}#1 \amp #2 \\ #3 \amp #4 \\ \end{array}\right]}\) \(\newcommand{\laspan}[1]{\text{Span}\{#1\}}\) \(\newcommand{\bcal}{\cal B}\) \(\newcommand{\ccal}{\cal C}\) \(\newcommand{\scal}{\cal S}\) \(\newcommand{\wcal}{\cal W}\) \(\newcommand{\ecal}{\cal E}\) \(\newcommand{\coords}[2]{\left\{#1\right\}_{#2}}\) \(\newcommand{\gray}[1]{\color{gray}{#1}}\) \(\newcommand{\lgray}[1]{\color{lightgray}{#1}}\) \(\newcommand{\rank}{\operatorname{rank}}\) \(\newcommand{\row}{\text{Row}}\) \(\newcommand{\col}{\text{Col}}\) \(\renewcommand{\row}{\text{Row}}\) \(\newcommand{\nul}{\text{Nul}}\) \(\newcommand{\var}{\text{Var}}\) \(\newcommand{\corr}{\text{corr}}\) \(\newcommand{\len}[1]{\left|#1\right|}\) \(\newcommand{\bbar}{\overline{\bvec}}\) \(\newcommand{\bhat}{\widehat{\bvec}}\) \(\newcommand{\bperp}{\bvec^\perp}\) \(\newcommand{\xhat}{\widehat{\xvec}}\) \(\newcommand{\vhat}{\widehat{\vvec}}\) \(\newcommand{\uhat}{\widehat{\uvec}}\) \(\newcommand{\what}{\widehat{\wvec}}\) \(\newcommand{\Sighat}{\widehat{\Sigma}}\) \(\newcommand{\lt}{<}\) \(\newcommand{\gt}{>}\) \(\newcommand{\amp}{&}\) \(\definecolor{fillinmathshade}{gray}{0.9}\)Scenario 25 – Baseline Reset and Contract Realignment
Scenario Context
Following scope reconciliation and stakeholder conflict in Scenario 24, it is now clear that:
-
The original scope baseline is no longer accurate
-
Informal enhancements have become embedded in the system
-
Stakeholder expectations have evolved
-
Budget and schedule assumptions have shifted
C-Bay has initiated a formal realignment effort to:
-
Reset scope baseline
-
Clarify deliverables
-
Reconcile cost and schedule
-
Establish clear control moving forward
ZynoxDev has responded with a formal proposal.
Email from Julie Rama
Subject: Project Realignment Proposal – Scope, Schedule, and Cost
Hi,
Following the recent scope reconciliation discussions, we have prepared a proposal to align the project moving forward.
1. Proposed Scope Baseline
We recommend redefining the project scope as follows:
-
Core Features (Original Scope) → Completed
-
Enhancements (Previously Informal) → Included as formal scope
-
Partial Features → Completed or removed based on prioritization
This reflects the system as it currently exists and stakeholder expectations.
2. Schedule Realignment
To accommodate the expanded scope and stabilization efforts:
-
Revised delivery timeline: +2 weeks beyond original plan
-
Adjusted milestone checkpoints for future iterations
3. Budget Adjustment
Based on current effort and scope expansion:
-
Proposed budget increase: +12–14%
-
Reflects:
-
Additional development effort
-
Increased QA cycles
-
Refactoring and stabilization work
-
4. Control Measures
To prevent further drift, we propose:
-
Strict change control for all future enhancements
-
Formal backlog prioritization reviews
-
Defined iteration scope boundaries
5. Request
Please review and confirm:
-
Acceptance of revised scope baseline
-
Approval of schedule adjustment
-
Approval of budget realignment
We believe this will establish a stable foundation moving forward.
Best,
Julie
Attachment A – Realignment Summary
| Area | Original | Revised |
|---|---|---|
| Scope | URD-defined | Expanded (includes enhancements) |
| Schedule | Original timeline | +2 weeks |
| Budget | Baseline | +12–14% |
Attachment B – Control Measures
-
Formal change request process required for all new features
-
Backlog review at start of each iteration
-
No in-iteration scope adjustments allowed
Student Assignment
You are the Project Manager at C-Bay.
You must now decide whether to:
-
Accept the proposed realignment
-
Modify the proposal
-
Reject elements of the proposal
This decision will define:
-
The new baseline for the project
-
The credibility of project control moving forward
-
The relationship with ZynoxDev
You must evaluate:
-
Whether the proposed scope is acceptable
-
Whether budget increase is justified
-
Whether schedule adjustment is reasonable
-
Whether control measures are sufficient
Prepare a formal written response to Julie Rama.
Required Submission Structure
Your memorandum must include:
1️⃣ Executive Position
-
Do you accept the realignment proposal?
-
What elements do you approve or reject?
-
Is the project now under control?
2️⃣ Scope Decision
-
Should all enhancements be formalized into scope?
-
Should any features be removed or deferred?
-
Is the revised scope appropriate?
3️⃣ Budget & Schedule Decision
-
Is +12–14% budget increase justified?
-
Is a +2 week delay acceptable?
-
Should adjustments be negotiated?
4️⃣ Contract & Control Alignment
-
Are proposed control measures sufficient?
-
Should additional controls be introduced?
-
How will future drift be prevented?
5️⃣ Risk Assessment
Identify and evaluate:
-
Budget overrun risk
-
Schedule extension risk
-
Scope misalignment risk
-
Governance failure risk
Assign likelihood and impact.
6️⃣ Strategic Positioning
-
How will you communicate this realignment internally?
-
How will you justify the changes to leadership?
-
How will you restore confidence in project control?
7️⃣ Directive to ZynoxDev
Provide a clear directive, such as:
-
Approve full realignment
-
Approve with modifications
-
Reject certain scope elements
-
Require revised proposal
-
Implement additional governance controls
Learning Focus
Scenario 25 introduces:
-
Formal baseline reset
-
Contract realignment
-
Converting informal history into structured agreement
-
Negotiation of cost, scope, and schedule simultaneously
-
Establishing control after drift
Students must demonstrate:
-
Strategic negotiation
-
Decision ownership
-
Balance between acceptance and control
-
Long-term thinking
Key Insight
A project can only be controlled once reality is acknowledged.
This scenario reinforces:
You cannot manage what is no longer aligned with the plan.
You must:
-
Update the plan
-
Or restore the plan
This marks a major turning point in the practicum.

