8.5: Submission Checklist and Final Assembly

  • Page ID
    52163
  • \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \( \newcommand{\dsum}{\displaystyle\sum\limits} \)

    \( \newcommand{\dint}{\displaystyle\int\limits} \)

    \( \newcommand{\dlim}{\displaystyle\lim\limits} \)

    \( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)

    ( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\id}{\mathrm{id}}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\kernel}{\mathrm{null}\,}\)

    \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\)

    \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\)

    \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)

    \( \newcommand{\vectorA}[1]{\vec{#1}}      % arrow\)

    \( \newcommand{\vectorAt}[1]{\vec{\text{#1}}}      % arrow\)

    \( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vectorC}[1]{\textbf{#1}} \)

    \( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)

    \( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)

    \( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)

    \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \(\newcommand{\longvect}{\overrightarrow}\)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \(\newcommand{\avec}{\mathbf a}\) \(\newcommand{\bvec}{\mathbf b}\) \(\newcommand{\cvec}{\mathbf c}\) \(\newcommand{\dvec}{\mathbf d}\) \(\newcommand{\dtil}{\widetilde{\mathbf d}}\) \(\newcommand{\evec}{\mathbf e}\) \(\newcommand{\fvec}{\mathbf f}\) \(\newcommand{\nvec}{\mathbf n}\) \(\newcommand{\pvec}{\mathbf p}\) \(\newcommand{\qvec}{\mathbf q}\) \(\newcommand{\svec}{\mathbf s}\) \(\newcommand{\tvec}{\mathbf t}\) \(\newcommand{\uvec}{\mathbf u}\) \(\newcommand{\vvec}{\mathbf v}\) \(\newcommand{\wvec}{\mathbf w}\) \(\newcommand{\xvec}{\mathbf x}\) \(\newcommand{\yvec}{\mathbf y}\) \(\newcommand{\zvec}{\mathbf z}\) \(\newcommand{\rvec}{\mathbf r}\) \(\newcommand{\mvec}{\mathbf m}\) \(\newcommand{\zerovec}{\mathbf 0}\) \(\newcommand{\onevec}{\mathbf 1}\) \(\newcommand{\real}{\mathbb R}\) \(\newcommand{\twovec}[2]{\left[\begin{array}{r}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\ctwovec}[2]{\left[\begin{array}{c}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\threevec}[3]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\cthreevec}[3]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\fourvec}[4]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\cfourvec}[4]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\fivevec}[5]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\cfivevec}[5]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\mattwo}[4]{\left[\begin{array}{rr}#1 \amp #2 \\ #3 \amp #4 \\ \end{array}\right]}\) \(\newcommand{\laspan}[1]{\text{Span}\{#1\}}\) \(\newcommand{\bcal}{\cal B}\) \(\newcommand{\ccal}{\cal C}\) \(\newcommand{\scal}{\cal S}\) \(\newcommand{\wcal}{\cal W}\) \(\newcommand{\ecal}{\cal E}\) \(\newcommand{\coords}[2]{\left\{#1\right\}_{#2}}\) \(\newcommand{\gray}[1]{\color{gray}{#1}}\) \(\newcommand{\lgray}[1]{\color{lightgray}{#1}}\) \(\newcommand{\rank}{\operatorname{rank}}\) \(\newcommand{\row}{\text{Row}}\) \(\newcommand{\col}{\text{Col}}\) \(\renewcommand{\row}{\text{Row}}\) \(\newcommand{\nul}{\text{Nul}}\) \(\newcommand{\var}{\text{Var}}\) \(\newcommand{\corr}{\text{corr}}\) \(\newcommand{\len}[1]{\left|#1\right|}\) \(\newcommand{\bbar}{\overline{\bvec}}\) \(\newcommand{\bhat}{\widehat{\bvec}}\) \(\newcommand{\bperp}{\bvec^\perp}\) \(\newcommand{\xhat}{\widehat{\xvec}}\) \(\newcommand{\vhat}{\widehat{\vvec}}\) \(\newcommand{\uhat}{\widehat{\uvec}}\) \(\newcommand{\what}{\widehat{\wvec}}\) \(\newcommand{\Sighat}{\widehat{\Sigma}}\) \(\newcommand{\lt}{<}\) \(\newcommand{\gt}{>}\) \(\newcommand{\amp}{&}\) \(\definecolor{fillinmathshade}{gray}{0.9}\)

    Submission Checklist & Final Assembly

    Before You Submit Your Closeout Package, Review This Checklist Carefully

    Your Chapter 6 deliverables complete the NovaMed Project Closeout based only on the first six weeks of execution. The quality of your closeout package depends not only on what you include, but on how well you assemble, justify, and organize your materials.

    Use this checklist to ensure that your final submission is complete, coherent, and professional.

    ✅ A. Required Deliverables (Must Submit All)

    1. Partial Acceptance Matrix

    Your matrix must include:

    • Milestones (Release 1–4 + Final Acceptance)

    • SOW due dates (for context)

    • Delivery status at Week 6

    • Acceptance status (Accept / Conditional / Reject / Cannot Evaluate)

    • Notes referencing SOW, SRS, HLDD, or memos

    File Name:
    CBay_AcceptanceMatrix_YourName.xlsx


    2. Documentation Verification Checklist

    Includes:

    • Required documentation (User Manual, Install Manual, Developer Manual, testing results, release notes, etc.)

    • Status: Delivered / Partial / Missing

    • Notes on completeness & accuracy

    File Name:
    CBay_DocumentationChecklist_YourName.docx


    3. Final Earned Value Summary

    Using Weeks 1–6 only:

    • PV, EV, AC

    • SV, CV

    • SPI, CPI

    • EAC, VAC

    • Final interpretation of project performance

    File Name:
    CBay_EVM_FinalSummary_YourName.xlsx


    4. Open Defect & Issue Disposition Log

    Lists all known issues from Weeks 1–6:

    • Defects from Week 4 memo

    • Integration failures (Week 6)

    • HLDD delay (Week 2)

    • Reporting failures

    • Unauthorized scope change

    • Staffing departure

    Includes disposition: Fix Now / Defer / Reject / Needs Clarification.

    File Name:
    CBay_DefectDisposition_YourName.docx


    5. Vendor Performance Evaluation

    Evaluate WinSoft based on:

    • Schedule discipline

    • Cost performance

    • Reporting quality

    • Communication & transparency

    • Deliverable quality

    • Responsiveness

    • Adherence to Contract & SOW

    File Name:
    CBay_VendorEvaluation_YourName.docx


    6. Final Acceptance Memo

    A decision memo from C-Bay to WinSoft:

    • Accept / Cannot Accept

    • Basis of your decision

    • Defects preventing acceptance

    • Outstanding documentation

    • Any required future actions

    • Contractual closing language

    File Name:
    CBay_FinalAcceptanceMemo_YourName.docx


    7. Closeout Summary Report

    Your leadership-facing summary, including:

    • Executive Summary

    • What was planned vs. what was achieved (Weeks 1–6)

    • EVM analysis

    • Key issues & defects

    • Acceptance conclusions

    • Vendor performance overview

    • Lessons learned

    • Recommendations for future action

    File Name:
    CBay_CloseoutReport_YourName.docx


    8. Final Reflection

    Your 1-page personal reflection on:

    • What you learned

    • How execution issues shape closing decisions

    • How you evaluated acceptance criteria

    • What you would do differently as a project leader

    File Name:
    CBay_CloseoutReflection_YourName.docx

    🔍 C. Quality Assurance Checklist (Final Review Before Submission)

    Completeness

    • All 8 required deliverables included

    • All files open correctly

    • Naming convention followed

    Documentation Alignment

    • Acceptance decisions reference SOW & SRS

    • Vendor evaluation references Contract & memos

    • EVM summary matches Weeks 1–6 numbers

    • Defects categorized correctly

    • Documentation checklist reflects Week 6 reality

    Professional Tone

    • Final Acceptance Memo reads like a leadership communication

    • No informal tone, emotional language, or unsupported claims

    • Recommendations are actionable and justified

    Accuracy & Insight

    • Earned Value interpretation is consistent

    • Closeout report synthesizes data coherently

    • Reflection demonstrates real learning

    🎯 D. What “Excellent” Work Looks Like

    A top-scoring submission will:

    • Identify patterns across the six weeks

    • Reference the proper contract/SOW sections

    • Use defect & EVM data to justify decisions

    • Provide a realistic and constructive vendor evaluation

    • Communicate clearly and professionally

    • Show leadership-level insight in the reflection

     


    8.5: Submission Checklist and Final Assembly is shared under a CC BY 4.0 license and was authored, remixed, and/or curated by LibreTexts.