5.3: What You Will Submit

  • Page ID
    52230
  • \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \( \newcommand{\dsum}{\displaystyle\sum\limits} \)

    \( \newcommand{\dint}{\displaystyle\int\limits} \)

    \( \newcommand{\dlim}{\displaystyle\lim\limits} \)

    \( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)

    ( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\id}{\mathrm{id}}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\kernel}{\mathrm{null}\,}\)

    \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\)

    \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\)

    \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)

    \( \newcommand{\vectorA}[1]{\vec{#1}}      % arrow\)

    \( \newcommand{\vectorAt}[1]{\vec{\text{#1}}}      % arrow\)

    \( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vectorC}[1]{\textbf{#1}} \)

    \( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)

    \( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)

    \( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)

    \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \(\newcommand{\longvect}{\overrightarrow}\)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \(\newcommand{\avec}{\mathbf a}\) \(\newcommand{\bvec}{\mathbf b}\) \(\newcommand{\cvec}{\mathbf c}\) \(\newcommand{\dvec}{\mathbf d}\) \(\newcommand{\dtil}{\widetilde{\mathbf d}}\) \(\newcommand{\evec}{\mathbf e}\) \(\newcommand{\fvec}{\mathbf f}\) \(\newcommand{\nvec}{\mathbf n}\) \(\newcommand{\pvec}{\mathbf p}\) \(\newcommand{\qvec}{\mathbf q}\) \(\newcommand{\svec}{\mathbf s}\) \(\newcommand{\tvec}{\mathbf t}\) \(\newcommand{\uvec}{\mathbf u}\) \(\newcommand{\vvec}{\mathbf v}\) \(\newcommand{\wvec}{\mathbf w}\) \(\newcommand{\xvec}{\mathbf x}\) \(\newcommand{\yvec}{\mathbf y}\) \(\newcommand{\zvec}{\mathbf z}\) \(\newcommand{\rvec}{\mathbf r}\) \(\newcommand{\mvec}{\mathbf m}\) \(\newcommand{\zerovec}{\mathbf 0}\) \(\newcommand{\onevec}{\mathbf 1}\) \(\newcommand{\real}{\mathbb R}\) \(\newcommand{\twovec}[2]{\left[\begin{array}{r}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\ctwovec}[2]{\left[\begin{array}{c}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\threevec}[3]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\cthreevec}[3]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\fourvec}[4]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\cfourvec}[4]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\fivevec}[5]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\cfivevec}[5]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\mattwo}[4]{\left[\begin{array}{rr}#1 \amp #2 \\ #3 \amp #4 \\ \end{array}\right]}\) \(\newcommand{\laspan}[1]{\text{Span}\{#1\}}\) \(\newcommand{\bcal}{\cal B}\) \(\newcommand{\ccal}{\cal C}\) \(\newcommand{\scal}{\cal S}\) \(\newcommand{\wcal}{\cal W}\) \(\newcommand{\ecal}{\cal E}\) \(\newcommand{\coords}[2]{\left\{#1\right\}_{#2}}\) \(\newcommand{\gray}[1]{\color{gray}{#1}}\) \(\newcommand{\lgray}[1]{\color{lightgray}{#1}}\) \(\newcommand{\rank}{\operatorname{rank}}\) \(\newcommand{\row}{\text{Row}}\) \(\newcommand{\col}{\text{Col}}\) \(\renewcommand{\row}{\text{Row}}\) \(\newcommand{\nul}{\text{Nul}}\) \(\newcommand{\var}{\text{Var}}\) \(\newcommand{\corr}{\text{corr}}\) \(\newcommand{\len}[1]{\left|#1\right|}\) \(\newcommand{\bbar}{\overline{\bvec}}\) \(\newcommand{\bhat}{\widehat{\bvec}}\) \(\newcommand{\bperp}{\bvec^\perp}\) \(\newcommand{\xhat}{\widehat{\xvec}}\) \(\newcommand{\vhat}{\widehat{\vvec}}\) \(\newcommand{\uhat}{\widehat{\uvec}}\) \(\newcommand{\what}{\widehat{\wvec}}\) \(\newcommand{\Sighat}{\widehat{\Sigma}}\) \(\newcommand{\lt}{<}\) \(\newcommand{\gt}{>}\) \(\newcommand{\amp}{&}\) \(\definecolor{fillinmathshade}{gray}{0.9}\)

    🎯 Purpose of This Submission

    In this milestone, your submission demonstrates that you can not only design a great project plan, but also estimate its financial cost responsibly and present it professionally.

    You are submitting a cost model that:

    • Reflects your full execution plan

    • Applies appropriate estimation methods

    • Provides clear logic and documentation

    • Supports stakeholder review and funding approval

    This is more than an academic assignment—your submission is your budget justification package. Treat it as if it were going into a live approval meeting with a project sponsor, finance lead, or executive committee.

    🗂️ What You Must Include

    Your submission must contain the following five structured components, in the order below:

    ✅ 1. Cost Categories and Input Summary

    What to include:

    • A categorized list of all labor and non-labor cost items

    • Clear labels for cost types: Labor vs. Non-Labor, Fixed vs. Variable, One-Time vs. Recurring

    • Classification of each cost (Direct vs. Indirect)

    • Notes on how the item was identified (e.g., WBS reference, tool usage, stakeholder event)

    📘 Deliverable Format:
    A well-organized table or matrix

    Cost Item Category Classification Description Source
    Business Analyst Labor Labor Direct, Variable 60 hours across Weeks 1–3 Milestone 3 effort estimates
    Cloud Hosting Non-Labor Fixed, Recurring 12 months of platform services Vendor pricing

    ✅ 2. Labor Cost Estimation Table

    What to include:

    • Task name or WBS ID

    • Role performing the task

    • Effort (in hours) from Milestone 3

    • Hourly rate per role

    • Total labor cost

    • Assumptions or utilization factors (e.g., full-time vs. 50% allocation)

    📘 Deliverable Format:
    Task-based estimation table

    Task Role Effort (hrs) Rate ($/hr) Total Cost Notes
    Conduct Interviews Business Analyst 16 hrs $85 $1,360 Full availability assumed

    ✅ 3. Non-Labor Cost Estimation Table

    What to include:

    • Item or service

    • Description of usage

    • Quantity and unit cost

    • Duration (if recurring)

    • Total calculated cost

    • Source or pricing assumption

    📘 Deliverable Format:
    Itemized estimation table

    Item Description Qty Unit Cost Duration Total Cost Source
    PM Software Project tool license 5 users $30/mo 6 months $900 Vendor site pricing

    ✅ 4. Total Budget and Allocation Model

    What to include:

    • Roll-up of all labor and non-labor costs

    • Optional: Phase-based, category-based, or deliverable-based views

    • Clearly labeled subtotals and grand total

    • Contingency added as a distinct line item (with justification)

    📘 Deliverable Format:
    Clean, scannable budget summary table

    Category Subtotal
    Labor $42,000
    Non-Labor $10,000
    Contingency (10%) $5,200
    Total Budget $57,200

    ✅ 5. Contingency and Funding Narrative

    What to include:

    • A brief paragraph (4–6 sentences) that summarizes:

      • What your budget includes

      • Where uncertainty exists

      • What risks justify contingency

      • What the funding enables in terms of project outcomes

    📘 Deliverable Format:
    Well-written paragraph, suitable for executive summary or sponsor presentation

    📘 Example:

    "This budget accounts for all labor and platform expenses associated with planning, design, build, testing, and transition for the UCMS Clinical Management System. Labor cost is derived from effort estimates built in Milestone 3, priced at blended market rates. Contingency has been included based on risk areas including stakeholder scheduling volatility and third-party vendor delays. This funding request supports a full launch readiness cycle by Q2 and ensures cross-functional delivery with sufficient coverage for training and risk mitigation."

    📁 File Organization and Submission Format

    Requirement Details
    File Format Submit in .docx or .pdf unless otherwise specified
    File Name Milestone4_Budget_YourTeamName.docx
    Document Order Follow the 5-section structure listed above
    Professionalism Tables aligned, no filler content, executive-ready tone
    Consistency Budget links back to the WBS, schedule, and roles used in Milestones 2 & 3