Skip to main content
Workforce LibreTexts

6.3: What You Will Submit

  • Page ID
    52238
  • \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \( \newcommand{\dsum}{\displaystyle\sum\limits} \)

    \( \newcommand{\dint}{\displaystyle\int\limits} \)

    \( \newcommand{\dlim}{\displaystyle\lim\limits} \)

    \( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)

    ( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\id}{\mathrm{id}}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\kernel}{\mathrm{null}\,}\)

    \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\)

    \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\)

    \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)

    \( \newcommand{\vectorA}[1]{\vec{#1}}      % arrow\)

    \( \newcommand{\vectorAt}[1]{\vec{\text{#1}}}      % arrow\)

    \( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vectorC}[1]{\textbf{#1}} \)

    \( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)

    \( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)

    \( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)

    \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \(\newcommand{\longvect}{\overrightarrow}\)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \(\newcommand{\avec}{\mathbf a}\) \(\newcommand{\bvec}{\mathbf b}\) \(\newcommand{\cvec}{\mathbf c}\) \(\newcommand{\dvec}{\mathbf d}\) \(\newcommand{\dtil}{\widetilde{\mathbf d}}\) \(\newcommand{\evec}{\mathbf e}\) \(\newcommand{\fvec}{\mathbf f}\) \(\newcommand{\nvec}{\mathbf n}\) \(\newcommand{\pvec}{\mathbf p}\) \(\newcommand{\qvec}{\mathbf q}\) \(\newcommand{\svec}{\mathbf s}\) \(\newcommand{\tvec}{\mathbf t}\) \(\newcommand{\uvec}{\mathbf u}\) \(\newcommand{\vvec}{\mathbf v}\) \(\newcommand{\wvec}{\mathbf w}\) \(\newcommand{\xvec}{\mathbf x}\) \(\newcommand{\yvec}{\mathbf y}\) \(\newcommand{\zvec}{\mathbf z}\) \(\newcommand{\rvec}{\mathbf r}\) \(\newcommand{\mvec}{\mathbf m}\) \(\newcommand{\zerovec}{\mathbf 0}\) \(\newcommand{\onevec}{\mathbf 1}\) \(\newcommand{\real}{\mathbb R}\) \(\newcommand{\twovec}[2]{\left[\begin{array}{r}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\ctwovec}[2]{\left[\begin{array}{c}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\threevec}[3]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\cthreevec}[3]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\fourvec}[4]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\cfourvec}[4]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\fivevec}[5]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\cfivevec}[5]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\mattwo}[4]{\left[\begin{array}{rr}#1 \amp #2 \\ #3 \amp #4 \\ \end{array}\right]}\) \(\newcommand{\laspan}[1]{\text{Span}\{#1\}}\) \(\newcommand{\bcal}{\cal B}\) \(\newcommand{\ccal}{\cal C}\) \(\newcommand{\scal}{\cal S}\) \(\newcommand{\wcal}{\cal W}\) \(\newcommand{\ecal}{\cal E}\) \(\newcommand{\coords}[2]{\left\{#1\right\}_{#2}}\) \(\newcommand{\gray}[1]{\color{gray}{#1}}\) \(\newcommand{\lgray}[1]{\color{lightgray}{#1}}\) \(\newcommand{\rank}{\operatorname{rank}}\) \(\newcommand{\row}{\text{Row}}\) \(\newcommand{\col}{\text{Col}}\) \(\renewcommand{\row}{\text{Row}}\) \(\newcommand{\nul}{\text{Nul}}\) \(\newcommand{\var}{\text{Var}}\) \(\newcommand{\corr}{\text{corr}}\) \(\newcommand{\len}[1]{\left|#1\right|}\) \(\newcommand{\bbar}{\overline{\bvec}}\) \(\newcommand{\bhat}{\widehat{\bvec}}\) \(\newcommand{\bperp}{\bvec^\perp}\) \(\newcommand{\xhat}{\widehat{\xvec}}\) \(\newcommand{\vhat}{\widehat{\vvec}}\) \(\newcommand{\uhat}{\widehat{\uvec}}\) \(\newcommand{\what}{\widehat{\wvec}}\) \(\newcommand{\Sighat}{\widehat{\Sigma}}\) \(\newcommand{\lt}{<}\) \(\newcommand{\gt}{>}\) \(\newcommand{\amp}{&}\) \(\definecolor{fillinmathshade}{gray}{0.9}\)

    Purpose of This Submission

    Your submission for this milestone demonstrates your team’s ability to move from planning into operational control. You are submitting a set of tools designed to:

    • Monitor scope completion and milestone health
    • Track actual progress against scheduled work
    • Detect delays or deviations in real time
    • Respond to scope creep, risks, or blockers
    • Communicate status effectively to internal and external stakeholders

    You are expected to submit a complete, cohesive Control Toolkit that could be used by a real project team to guide execution and reporting.

    Overview of Required Components

    Component Purpose
    1. Scope Control Register Track all major deliverables, their completion status, and any scope change activity
    2. Schedule Progress Tracker Track progress (% complete, dates, risk flags) for all critical tasks and milestones
    3. Change & Escalation Protocol Provide clear rules and structure for how changes, delays, and blockers are escalated and resolved
    4. Control Dashboard (Lite) One-page status summary that presents health of the project to sponsors and stakeholders

    Each component must be:

    • Logically linked to your previously submitted WBS and milestone schedule
    • Professionally formatted and usable in an execution context
    • Clean, complete, and readable by someone who did not help build the plan

    1. Scope Control Register

    What to include:

    • Complete list of major deliverables (Level 2/3 WBS)
    • Owner or responsible party
    • Original due dates
    • Current status (e.g., Not Started, In Progress, Complete, Blocked)
    • Percent complete (optional but recommended)
    • Scope change flag (Y/N)
    • Notes on scope deviations or risks
    • Column to track formal approval status if needed

    Submission Format:
    Editable spreadsheet (.xlsx, .csv, or embedded in Word/Google Doc table)

    Example Row:

    WBS ID Deliverable Owner Due Date Status % Complete Scope Change Notes
    2.1.3 Training Material Draft Instructional Lead Apr 5 In Progress 40% No SME review scheduled for Apr 3

    2. Schedule Progress Tracker

    What to include:

    • Critical tasks, deliverables, and milestones
    • Planned start and end dates
    • Actual start and end dates (if known)
    • Percent complete OR status indicator (RAG color or On Track / At Risk / Delayed)
    • Days behind/ahead (optional)
    • Short notes or blockers field
    • Ownership clearly indicated

    Submission Format:

    • Spreadsheet or Gantt-style chart (.xlsx, .docx table, or timeline tool export)
    • Optional: add progress bars, color-coding, conditional formatting for status

    Example:

    Task Owner Planned End Actual End Status % Complete Notes
    Finalize Requirements BA Mar 10 Mar 12 🔴 Delayed 100% Approved late due to stakeholder review

    3. Change and Escalation Protocol

    What to include:

    • A short written procedure or flowchart outlining how issues are escalated
    • Defined triggers for scope or schedule escalation
    • Escalation levels (Team → PM → Sponsor)
    • Table or matrix showing response timeline and decision owner
    • Change Log format for tracking all raised and resolved issues

    Submission Format:

    • PDF, DOCX, or slide showing escalation diagram + table
    • Include Change Log table with at least 1–2 mock entries

    Example Change Log Entry:

    Change ID Description Type Date Owner Impact Status
    SC-001 Add security audit step to build phase Scope Apr 1 PM +12 hrs Approved

    4. Control Dashboard 

    What to include:

    • Project name, date, and overall status indicator
    • Milestone summary with status (green/yellow/red)
    • High-level progress indicators (e.g., 70% complete, 4 of 6 milestones met)
    • Top 3 active risks or issues with owners
    • Scope change summary or “no changes this cycle”
    • Next major actions or decisions due

    Submission Format:

    • 1-page PDF, DOCX, or slide deck
    • Designed for visual clarity: icons, tables, status bars, RAG indicators
    • Should be scannable in under 60 seconds

    Example Snapshot:

    UCMS Clinical System – Week 6 Dashboard
    Overall Status: 🟡 At Risk (Training Delay)
    
    Milestones:
    - Requirements Signed Off ✅
    - Training In Progress 🟡 (2 of 4 sessions complete)
    - Go-Live Prep 🔴 (Blocked by vendor access)
    
    % Complete: 68% of WBS tasks delivered
    
    Top Risks:
    1. SME unavailable for Testing Review (Owner: QA Lead)
    2. Platform license delayed (Owner: PM)
    
    Scope Changes:
    - SC-001: Audit step added, Approved Apr 1
    
    Next Actions:
    - Finish Training Sessions (Due Apr 7)
    - Confirm Pilot Launch Readiness (Due Apr 10)
    

    Submission Format Guidelines

    Requirement Details
    File Type Submit as PDF, DOCX, XLSX, or Google Doc/Sheet link (as instructed)
    File Name Milestone5_ControlToolkit_TeamName.docx (or equivalent)
    Organization Submit as one document (preferred) or clearly labeled separate files
    Professionalism Clean formatting, no placeholder text, real sample data
    Versioning Optional: add "Week 6 Draft" or "Final Submission" tag in footer/header

    Quality Criteria for Submission

    Quality Area What We’re Looking For
    Traceability Control tools map directly to WBS, schedule, and scope from earlier milestones
    Clarity Tables are readable, indicators are clear, status is not buried in long text
    Usability Tools are designed for actual execution—not just for the assignment
    Completeness All required components are present and populated with real sample data
    Professionalism Layout is clean, consistent; tone is sponsor-facing and execution-ready

     


    6.3: What You Will Submit is shared under a CC BY 4.0 license and was authored, remixed, and/or curated by LibreTexts.

    • Was this article helpful?