1.11: Value Engineering

  • Page ID
    41272
  • \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \( \newcommand{\id}{\mathrm{id}}\) \( \newcommand{\Span}{\mathrm{span}}\)

    ( \newcommand{\kernel}{\mathrm{null}\,}\) \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\) \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\) \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\id}{\mathrm{id}}\)

    \( \newcommand{\Span}{\mathrm{span}}\)

    \( \newcommand{\kernel}{\mathrm{null}\,}\)

    \( \newcommand{\range}{\mathrm{range}\,}\)

    \( \newcommand{\RealPart}{\mathrm{Re}}\)

    \( \newcommand{\ImaginaryPart}{\mathrm{Im}}\)

    \( \newcommand{\Argument}{\mathrm{Arg}}\)

    \( \newcommand{\norm}[1]{\| #1 \|}\)

    \( \newcommand{\inner}[2]{\langle #1, #2 \rangle}\)

    \( \newcommand{\Span}{\mathrm{span}}\) \( \newcommand{\AA}{\unicode[.8,0]{x212B}}\)

    \( \newcommand{\vectorA}[1]{\vec{#1}}      % arrow\)

    \( \newcommand{\vectorAt}[1]{\vec{\text{#1}}}      % arrow\)

    \( \newcommand{\vectorB}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vectorC}[1]{\textbf{#1}} \)

    \( \newcommand{\vectorD}[1]{\overrightarrow{#1}} \)

    \( \newcommand{\vectorDt}[1]{\overrightarrow{\text{#1}}} \)

    \( \newcommand{\vectE}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash{\mathbf {#1}}}} \)

    \( \newcommand{\vecs}[1]{\overset { \scriptstyle \rightharpoonup} {\mathbf{#1}} } \)

    \( \newcommand{\vecd}[1]{\overset{-\!-\!\rightharpoonup}{\vphantom{a}\smash {#1}}} \)

    \(\newcommand{\avec}{\mathbf a}\) \(\newcommand{\bvec}{\mathbf b}\) \(\newcommand{\cvec}{\mathbf c}\) \(\newcommand{\dvec}{\mathbf d}\) \(\newcommand{\dtil}{\widetilde{\mathbf d}}\) \(\newcommand{\evec}{\mathbf e}\) \(\newcommand{\fvec}{\mathbf f}\) \(\newcommand{\nvec}{\mathbf n}\) \(\newcommand{\pvec}{\mathbf p}\) \(\newcommand{\qvec}{\mathbf q}\) \(\newcommand{\svec}{\mathbf s}\) \(\newcommand{\tvec}{\mathbf t}\) \(\newcommand{\uvec}{\mathbf u}\) \(\newcommand{\vvec}{\mathbf v}\) \(\newcommand{\wvec}{\mathbf w}\) \(\newcommand{\xvec}{\mathbf x}\) \(\newcommand{\yvec}{\mathbf y}\) \(\newcommand{\zvec}{\mathbf z}\) \(\newcommand{\rvec}{\mathbf r}\) \(\newcommand{\mvec}{\mathbf m}\) \(\newcommand{\zerovec}{\mathbf 0}\) \(\newcommand{\onevec}{\mathbf 1}\) \(\newcommand{\real}{\mathbb R}\) \(\newcommand{\twovec}[2]{\left[\begin{array}{r}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\ctwovec}[2]{\left[\begin{array}{c}#1 \\ #2 \end{array}\right]}\) \(\newcommand{\threevec}[3]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\cthreevec}[3]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \end{array}\right]}\) \(\newcommand{\fourvec}[4]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\cfourvec}[4]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \end{array}\right]}\) \(\newcommand{\fivevec}[5]{\left[\begin{array}{r}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\cfivevec}[5]{\left[\begin{array}{c}#1 \\ #2 \\ #3 \\ #4 \\ #5 \\ \end{array}\right]}\) \(\newcommand{\mattwo}[4]{\left[\begin{array}{rr}#1 \amp #2 \\ #3 \amp #4 \\ \end{array}\right]}\) \(\newcommand{\laspan}[1]{\text{Span}\{#1\}}\) \(\newcommand{\bcal}{\cal B}\) \(\newcommand{\ccal}{\cal C}\) \(\newcommand{\scal}{\cal S}\) \(\newcommand{\wcal}{\cal W}\) \(\newcommand{\ecal}{\cal E}\) \(\newcommand{\coords}[2]{\left\{#1\right\}_{#2}}\) \(\newcommand{\gray}[1]{\color{gray}{#1}}\) \(\newcommand{\lgray}[1]{\color{lightgray}{#1}}\) \(\newcommand{\rank}{\operatorname{rank}}\) \(\newcommand{\row}{\text{Row}}\) \(\newcommand{\col}{\text{Col}}\) \(\renewcommand{\row}{\text{Row}}\) \(\newcommand{\nul}{\text{Nul}}\) \(\newcommand{\var}{\text{Var}}\) \(\newcommand{\corr}{\text{corr}}\) \(\newcommand{\len}[1]{\left|#1\right|}\) \(\newcommand{\bbar}{\overline{\bvec}}\) \(\newcommand{\bhat}{\widehat{\bvec}}\) \(\newcommand{\bperp}{\bvec^\perp}\) \(\newcommand{\xhat}{\widehat{\xvec}}\) \(\newcommand{\vhat}{\widehat{\vvec}}\) \(\newcommand{\uhat}{\widehat{\uvec}}\) \(\newcommand{\what}{\widehat{\wvec}}\) \(\newcommand{\Sighat}{\widehat{\Sigma}}\) \(\newcommand{\lt}{<}\) \(\newcommand{\gt}{>}\) \(\newcommand{\amp}{&}\) \(\definecolor{fillinmathshade}{gray}{0.9}\)
    Learning Objectives

    After reading this chapter, you should be able to:

    • Define Value Engineering in the context of delivering a construction project.
    • Understand the core characteristics of a valuable VE element.

    Defining Value

    The key word in ‘value engineering’ is ‘value’. One common definition of value is ‘what an owner is willing to pay for’. This leaves a lot to be defined, but certainly clarifies that the project team should be focused on providing benefit to an owner, the entity that is ultimately paying for all costs on a project. This requires the clear interpretation of ‘what provides value to the owner’.

    Another way to look at value is through an equation, where value = Function Performance / Resources.

    Defining Value Engineering (VE)

    Value Engineering (VE) is defined by the Office of Management and Budget as ‘an organized effort directed at analyzing the functions of systems, equipment, facilities, services, and supplies for the purpose of achieving the essential functions at the lowest life-cycle cost consistent with required performance, reliability, quality, and safety. (OMB, Circular No. A-131, 1993). In the Whole Building Design Guide, Cullen (2016) defined Value Engineering as ‘a conscious and explicit set of disciplined procedures designed to seek out optimum value for both initial and long-term investment.’ There are several commonalities in these definitions, including:

    • Life-cycle cost: A focus beyond just design and construction costs
    • Value optimization: Seeking cost-effective solutions to optimize the value to the owner
    • Disciplined process: The team should apply a conscious and disciplined process

    It is also important to note items that should not be considered within the definition of value engineering. Cullen (2016) states ‘Value Engineering is not a design/peer review or a cost-cutting exercise.’ This is very important to note since many people may refer to cost-cutting approaches as VE, when they are simply trying to reduce cost and reduce value at the same time.

    The Value Engineering Process

    A key element of VE is to ensure that you follow a rigorous, documented process. There is not one commonly accepted standard process, but there are several documented process descriptions that you can follow. One option is the process defined within the VE

    A more concise process has been outlined by SAVE International () in their Value Methodology Guide. This process contains 8 steps

    1. Preparation:
    2. Information:
    3. Function Analysis:
    4. Creativity:
    5. Evaluation:
    6. Development:
    7. Presentation:
    8. Implementation:

    https://www.value-eng.org/page/AboutVM

    A figure with the phases in VE Job Plan, including Orientation, Information, Function Analysis, Creative, Evaluation, Development, Presentation, and Implementation, along with subprocesses for each.
    Fig. 1: Depiction of VE Job Plan Phases

    as prescribed by SAVE International:
    The VE Job Plan follows five key steps:
    Information Phase
    Speculation (Creative) Phase
    Evaluation (Analysis) Phase
    Development Phase (Value Management Proposals)
    Presentation Phase (Report/Oral Presentation)
    These five key steps are described as follows:

    Examples of Value Engineering Proposals

    VE Process Documentation

    The outcome of the VE process should be monitored and managed. One part of monitoring the process is to maintain a log of the VE suggestions. Most collaborative online project management tools have a location to manage and track VE proposals in an online database. Alternatively, a designer or contractor can track VE proposals in a simple spreadsheet. An example setup with several simple sample proposals in Figure 2.

    Sample Value Engineering Table with headings for VE Proposal Number, Description, Data Submitted, Date of Decision, Building Documents, Trades, Redesign Impact, Schedule Impact, Cost Confirmed, Proposed Cost Revision, Decition, and Comments
    Figure 2: Value Engineering Proposal Log Example

    Review Questions

     

    References and Additional Resources:

    Cullen, S. (2016). ‘Value Engineering.’ Whole Building Design Guide, National Institut of Building Sciences. accessed on May 25, 2022, available at https://www.wbdg.org/resources/value-engineering.

    Office of Management and Budget. (1993). ‘Subject: Value Engineering.’ Circular No. A-131, available at https://georgewbush-whitehouse.archi...a131/a131.html

    Office of Deputy Assistant Secretary of Defense. (2011).


    This page titled 1.11: Value Engineering is shared under a CC BY-NC-SA 4.0 license and was authored, remixed, and/or curated by John Messner via source content that was edited to the style and standards of the LibreTexts platform.